As the field of environmental planning has evolved, a variety of documents have been produced to assist practitioners. These documents include the trilogy of Watershed Planning documents (MOEE, MNR, 1993), as well as others (Science and Technology Task Group, 1995; CVC, 1996). Collectively, these documents provide:
The objective of this chapter will be to draw upon the above noted documents together with other publications (including approximately 100 subwatershed plans that have been completed within Ontario) in order to:
Within each municipality, there will be differences as to how municipal land use and environmental planning will be undertaken. It is, therefore, not possible to define a process that is applicable to all municipalities for all types of studies. The intent of this section, therefore, will be to describe environmental and municipal land use planning in general.
Figure 2.1 illustrates general inter-relationships between municipal land use and environmental planning. The agencies that are typically involved with the review of documents at each phase are listed. Also provided (Figure 2.2) is a graphical representation of each of the four types of environmental studies. This graphic provides an overview of the scale of each study and, therefore, the degree of detail (or type of product) to be produced.
Provided below is a brief description of each of the environmental planning studies (i.e., Watershed Plan, Subwatershed Plan, Environmental Management Plan and Environmental/ Stormwater Management Plan) that may be undertaken. The objective of this section is to indicate what each type of plan typically provides. Several agencies have produced procedural manuals for environmental planning studies.
There may be other terms used for each type of plan in different jurisdictions. It is important to note the level of detail for each type of plan. In some cases the plans or elements of the plans may be combined.
Implicit in the watershed and subwatershed planning process is the uncertainty associated with deriving environmental form, functions and linkages, and forecasting future impacts based on land use and land management changes. The concept of adaptive environmental management recognizes this uncertainty, acknowledges learning through experimentation, and promotes using the knowledge gained to direct changes in management activities.
In order to measure the success of a watershed and subwatershed plan, it is imperative that clearly defined goals and objectives be formulated, and that a monitoring plan be implemented that provides the information necessary to evaluate whether the goals and objectives are being met. Changes to the recommended plan may be necessary if the results of the monitoring show that the objectives are not being achieved. As the process moves from the watershed, subwatershed and environmental management plans to the stormwater management report, management decisions can be adapted to better fit the local circumstances of each subwatershed, tributary and plan of subdivision. This approach allows for flexibility, consensus building and joint learning by managers of the environment, proponents for change and the public.
Undertaking environmental planning studies in concert with municipal land use studies will reduce the amount of work to be undertaken and streamline the review process, provided the proper expertise and representation from the agencies, public and consultants is available at the appropriate time (Figure 2.1).
Figure 2.1: General Relationship Between the Environmental Planning and the Municipal Land Use
Planning Process

Most stakeholders are involved at the initial stages where key decisions on broad issues (e.g., establishing goals/objectives, incorporating public input, establishing an implementation process) are required. Once consensus has been achieved for issues at the subwatershed or watershed scale, fewer agencies are generally required to review subsequent documents (e.g., EMPs, Environmental/SWM Plans).
As the process has evolved, so too have the disciplines required to undertake and review the studies. The expertise required for each study is dependent upon the level of detail required. However, in general, both the proponent and review agency require expertise in:
As is illustrated in Figure 2.2, watershed plans deal with the area drained by a major river (e.g., Credit, Grand, Rideau, Don, Thames) and its tributaries. The study area defined by the natural drainage boundaries of the watershed is considerable and usually at least 1,000 km².
A watershed plan is generally of value for addressing environmental issues associated with studies on the scale of an Official Plan. The study may be used to provide an overall picture as to how land use practices have influenced environmental resources or how land use changes should take place without causing adverse impacts to the watershed resources. Along with the strategic direction, the document may contain recommendations on implementation and funding, as well as resource management goals and objectives.
The watershed plan also provides direction for subsequent subwatershed studies. In this regard, information pertaining to resources, constraints, sources of contamination, key issues, resource goals and environmental targets may be provided.
The area under consideration in a subwatershed plan is typically 50 to 200 km². In some jurisdictions it is the first document produced. It is at this stage that all relevant agencies and the public participate. With a broad range of input being received and with the proper technical and implementation steps being undertaken, it should be possible to carry out subsequent studies at a
Figure 2.2: Graphical Representation of Environmental Studies

much smaller scale (typically at a tributary or Secondary Plan level). The key steps of a subwatershed plan are shown in Figure 2.3, and are briefly described below.
Collect Background Information
The initial step involves the collection of background information. This may include relevant
reports and base maps, as well as historical information that may be of value for defining
change within the subwatershed over time. The relationship of the subwatershed study to a
watershed plan, or other urban drainage, land use and planning studies should also be defined.
Establish Existing Environmental Conditions
A series of technical studies will be undertaken to establish existing environmental conditions.
In some cases, the information will be available from previous studies, while in others some
field work will be required. Typical component studies that need to be undertaken include:
These component studies will identify the location, areal extent, present status, significance and sensitivity of the existing natural environment within the subwatershed.
Identify Form, Function and Linkage of Natural Systems
The inter-relationships between the different resources need to be defined. This is done, in
part, via an overlay process using GIS and by assessing the technical information collected
in the previous step. The inter-relationships (e.g., the presence of a high quality fishery
in catchment areas containing good riparian cover, high recharge and wetlands) are important
in order to identify key attributes which need to be protected or restored.
Establish Environmental Goals and Objectives
An understanding of the existing conditions and linkages will assist stakeholders in defining
environmental goals and objectives for the subwatershed. These goals and objectives will
be used
Figure 2.3: Components of a Subwatershed Plan
as a basis for developing alternate subwatershed management strategies, and will also likely be used in subsequent, more detailed studies.
Develop and Evaluate Alternative Subwatershed Management Strategies
Alternative management strategies will be developed for the subwatershed which involve various
combinations of management options, including SWMPs. When implemented collectively, the management
options contained in each alternative are sufficient to meet the defined environmental goals
and objectives for the subwatershed.
Select Preferred Strategy
A preferred strategy is selected from the alternatives based on criteria which may include:
Describe Recommended Plan
The Recommended Plan for the Preferred Strategy will specify areas for protection, restoration
and/or enhancement. It will also identify areas which are developable, or developable subject
to further study. Typically, the Recommended Plan will also provide a general description
of each SWMP type, together with items relating to technical considerations, social, economic
and environmental benefit, environmental criteria, land requirements/impact and approximate
cost.
Implementation Plan
This part of the study will provide direction with respect to the steps which are necessary
to implement the recommended plan. Components of the implementation plan include:
As was stated previously, one of the objectives of a Subwatershed Plan is to provide information that may be used in subsequent, more detailed studies. One product that has been produced in several subwatershed studies is a Fact Sheet. Table 2.1 shows a fact sheet for a tributary within the subwatershed. Fact Sheets are often used to summarize key resources and targets, and may be used as a basis to establish the appropriate studies and measures to be undertaken, typically at the Official Plan Amendment or Secondary Plan stage.
The Environmental Management Plan (also referred to as an Environmental Impact Report, Environmental Area Plan or Master Environmental Servicing Plan) is typically carried out prior to consideration of Draft Plan Approval. The relationship of the EMP to other studies is shown in Figures 2.1 and 2.2.
Whereas watershed and subwatershed plans have been ongoing since the late 1980s, EMPs are a relatively new study. The deliverables from an EMP, therefore, are not as consistent from jurisdiction to jurisdiction. The typical area under consideration for an EMP is 2 to 10 km². The boundaries for the EMP may match the tributary subcatchment boundary or Secondary Plan boundary or a portion thereof.
With respect to the level of detail of the EMP, one of the objectives of the Subwatershed Plan was to provide sufficient detail so that future work would not be required beyond the tributary or Secondary Plan level. In an analogous manner, the EMP should be of sufficient detail that individual subdivision plans may proceed pending the completion of the EMP. Provided below is an overview of the components to be undertaken in an EMP.
Review Existing Information
All existing background information should be reviewed to confirm the level of detail and suitability
for use in the EMP. Information will be available from the subwatershed study, as well as
other studies completed within the study area. Relevant information may include:
Table 2.1: Credit River Subwatershed No. 19 – Eastern Tributary Fact Sheet
Environmental ResourcesStable natural channel systems with isolated impacts from rural land use practices (cattle crossings)
Source: Aquafor Beech Ltd., Environmental Planning for the Credit River Headwaters Subwatershed No. 19, prepared for CVC, 1997.
Define Existing Environmental Conditions and Establish Constraint/Opportunity Mapping
Existing information should be utilized and further study should be focussed on filling gaps
and enhancing the understanding of key resources. Detailed constraint and opportunity mapping
will be prepared which describes the environmental resources, together with the associated
land requirements.
The smaller scale analysis done for an EMP allows knowledge to be refined and more specific deliverables (Table 2.2) to be provided, as compared to a Subwatershed Study.
Establish Preferred Environmental and Stormwater Management Strategy
Typically, impact assessments are carried out (i.e., how does the hydrologic cycle change, how
will increases in metals loadings impact fisheries) for the proposed land use. Alternative
management strategies are developed, each including a series of environmental and stormwater
management practices. Collectively, the management practices will ensure that the environmental
resources are protected, restored or enhanced in accordance with defined goals and objectives.
Comparative evaluation of the strategies will lead to the selection of the preferred alternative.
Preparation of the Environmental Management Plan
An Environmental Management Plan which summarizes the findings of the previous steps should
be prepared. It is important to ensure that the plan highlights the deliverables and is of
sufficient detail such that all remaining environmental and/or stormwater management work
may be completed as conditions of the Draft or Site Plan stage. Key deliverables may include:
Other deliverables that may be presented, depending upon the level of detail and preference/requirements of the agencies include:
Table 2.2: Detailed Component Studies of an Environmental Management Plan
The Environmental/Stormwater Management Report is generally prepared in order to meet conditions set at the Draft Plan or Site Plan stage. The plan provides details with respect to the proposed environmental and stormwater management measures, and is usually submitted with grading and erosion plans and site servicing plans.
Several documents detail the requirements of these reports. The specific requirements will vary from municipality to municipality. The components of the study will also vary depending upon whether an EMP and/or subwatershed study has been completed.
Typical deliverables from an Environmental/Stormwater Management Report include:
Figure 2.1 shows the stakeholders who are involved at each phase of the review process. The review process, as shown, involves a majority of the stakeholders at the initial stages where key decisions involving a number of issues (e.g., establishing goals/objectives, incorporating public input, establishing an implementation process) are required. Once consensus has been achieved for a majority of issues at the subwatershed or watershed scale, then fewer agencies are generally required to review subsequent documents (e.g., EMPs, Environmental/SWM Plans).
Good planning which has regard for the need for stormwater management at the outset, combined with a recognition of the ecological attributes and functions of the watershed, provides the fundamental basis for achieving stormwater quality and quantity improvement efficiently and cost effectively. At this scale, stormwater management opportunities afforded by the physiographic and ecological features of the watershed can be identified, and capitalized upon. Areas where soils are permeable and suited to infiltration, existing vegetation communities which can function as biofilters and landforms that are naturally conducive to the implementation of detention initiatives will all be identified along with a suite of other characteristics which may be preserved or modified to achieve stormwater management objectives. The watershed planning approach, which is now ingrained within the municipal planning process, ensures that the important features and other interrelated factors are identified and understood at a regional scale. As a result, stormwater management opportunities afforded by the existing natural heritage features and functional systems are identified early in the process. This helps ensure that these opportunities will not be overlooked or lost when stormwater management initiatives are implemented at a site-specific scale.
At the watershed scale, the framework for the generation of a stormwater management system, which is integrated with the environment, is established. Effective stormwater management solutions to be explored at a watershed scale are rooted in a recognition of the value and potential function of the existing physical and ecological characteristics of the region. The following examples are provided:
Watershed planning is the most effective means of ensuring that responsible stormwater management solutions that are fully integrated with the regional ecosystem are achieved. It is also important to consistently apply this ecosystem-based approach at the community and site-specific levels to ensure that stormwater management opportunities afforded by site and context are identified and capitalized upon.
The term ‘community’ in this context is used to describe a level of planning at which the design for a ‘community’ is being resolved and may include the preparation of a secondary plan, a design plan for a development or a plan of a subdivision. Subdivision/site planning is described in more detail in Appendix A. At this scale, where land use patterns, road networks and open space systems are being defined, a range of opportunities to implement integrated solutions is afforded.
Consistent with the principle of watershed planning, solutions should be founded on a recognition of the natural heritage attributes of the site, including landform, vegetation, water resources, soil types and aquatic and terrestrial habitats. The system of open spaces is recognized as the most obvious opportunity to integrate stormwater management solutions successfully within the design of a community. However, there are numerous other opportunities to achieve stormwater management objectives as well as other multiple ecological, functional, social and economic objectives at this scale.
The open space system should be defined with the vision of establishing a network of natural features and complementary and compatible land uses which will be the spine or centerpiece of the community. The design for the open space system should be conceived with the goals of preserving existing resources, enhancing the overall ecological integrity of the site and providing recreational, social and educational benefits. The integration of stormwater management initiatives as components of the open space system contributes to the realization of these goals by increasing the physical area of available open space, enhancing terrestrial and aquatic habitat diversity and enhancing recreational and educational opportunities. The following are examples of techniques which have been applied to integrate stormwater management initiatives and enhance the open space network:
The breadth of opportunity to implement innovative solutions is expanded when the open space network is comprised of a cohesive system of natural areas, parks, school yards, stormwater management facilities, trails and linkages rather than a collection of isolated and disjointed parcels. The former affords a wider range of possibilities to integrate different types of SWMPs in series. Opportunities are lost when proposed stormwater management facilities are relegated to ‘leftover’ spaces rather than being considered as integral components and potential amenities within a development. A well executed open space network, which includes stormwater management facilities, has been proven to enhance the marketability of a development by establishing a character for the community and increasing the range of available amenities. In considering the design of the open space network, emphasis should be placed on establishing a seamless system of spaces with complementary uses built upon the existing natural features of the site.
Stormwater management solutions can be applied to the municipal network of roads within a community. Although much more constrained by requirements related to servicing, alignment, safety and gradient than the open space system, road right-of-ways present the opportunity to implement simple, cost-effective and beneficial stormwater management solutions. References for guidance on Ministry of Transportation (MTO) requirements for provincial highways are mentioned in Section 3.1.
A reduction in the width of the paved cross section of the road affords benefits such as:
Not only effective in terms of stormwater quality improvement, the implementation of grassed swales can result in substantial savings in cost when compared with conventional storm sewer servicing. Grassed swales also provide benefits related to snow storage and groundwater recharge where appropriate soil conditions exist.
Although not regarded as durable and sustainable for universal application, porous pavement, in the form of granular or precast concrete unit paving can be used in appropriate areas. Such areas include the shoulder of the road to provide a transition between the travelled surface and the grassed swale, in the centre of cul-de-sacs or in parking lanes. When used in these applications, porous pavement provides practical benefits as well as benefits related to water quality improvement and aesthetics.
Within the road right-of-way, there are a number of small areas well suited to the implementation of pocket detention facilities or biofilters. Cul-de-sac islands, medians, boulevards, roundabout islands, and in the case of limited access routes, leftover land within interchanges, should be considered as potential sites to detain stormwater and settle out pollutants. These areas can be paved or landscaped to integrate them into the aesthetics of a streetscape or character of the development. Although the sizes of these facilities are limited, collectively, significant stormwater management benefits can be achieved.
Increasing canopy cover in the urban context is a simple, effective means to intercept rainfall before it comes into contact with the ground and becomes runoff. In addition, through the process of transpiration, trees can extract moisture from the subsurface and discharge it into the atmosphere. Studies have shown that a mature willow tree can transpire approximately 750 litres of water during a single summer day. Increased planting of large canopy trees in the vicinity of streets, parking lots and other impervious surfaces may contribute to reduced rates of runoff in addition to affording benefits related to the production of oxygen, temperature reduction, habitat enhancement and aesthetics.
Lot configuration and grading are key factors in determining the extent to which lot level controls such as roof leader disconnection, vegetated filter strips and depression storage can be implemented as well as their effectiveness. Lot layout and grading should be defined with an emphasis not only on achieving maximum yield but also with the objective of maximizing the potential to implement lot level controls effectively.
Compact building forms such as townhouses, fourplexes, and clusters make available more open space and, consequently, greater opportunities to implement effective landscape-based stormwater management solutions than more conventional detached residential forms. The resultant increase in open space afforded by compact building forms provides the following stormwater management benefits:
Although built form will largely be dictated by market demand, the viability of compact built form options should be explored as a component of the integrated design process.
The most successful plan for a community is one that is developed using an open-minded approach that is focussed on defining a vision which recognizes the value of existing site resources and integrates environmental, social and functional objectives within a cohesive system.
Subwatershed planning and other planning exercises on a catchment basis provide the step-by-step method for evaluating the impacts of different forms and degrees of development on receiving waters. In some tributaries or subwatersheds draining to sensitive aquatic features, impacts may accumulate over time (due to the time for urbanization to be completed) and over space and the effectiveness of mitigating measures may be uncertain. To maintain the integrity of ecosystems, essential planning tools include scientific data documenting the effectiveness of mitigating measures and the consideration of cumulative effects.
In order to evaluate the management options and different types of SWMPs, it is necessary to formulate alternative plans which use various combination of options. All types of SWMPs are used in the formulation of alternative plans. Situations arise where a problem is attributable to a specific source and can be addressed through a specific option. This will, however, be the exception, rather than the rule. Most problems originate from a variety of sources and require a variety of management actions. Concern for stream temperature impacts on fisheries may, for instance, require protection of groundwater discharge areas and sources, restoration of stream canopy, creation of in-stream refuge areas, and use of particular stormwater SWMP types in urban development. No single option can solve the problem and it is necessary to examine the effects of the complete suite of options. The individual options may be the responsibility of different groups, both private and governmental, and it is implicit in the evaluation and assessment that all parties will implement those options which are their responsibility.
There is a second important factor in the formulation of alternative plans for evaluation, and that is the assessment of cumulative impact. Land use change produces both direct and immediately observable impacts and more gradual impacts which may build up to critical levels as growth proceeds, for example, the impacts of imperviousness on benthic organisms and stream stability as outlined in Chapter 1. A range of options aimed at addressing a particular problem may cease to be sufficient, if too much development takes place. The alternative plans must therefore be evaluated not only against each other, but also under a range of growth conditions.
While it is not possible to specify the alternative plans to be considered for watershed plans/ subwatershed plans on a generic basis, a few alternatives which contrast the potential range of impacts should be utilized. The alternatives would normally be evaluated in a cumulative manner with the management options which perform well being carried forward. This allows the assessment of increasing levels of stress being applied to the watershed/subwatershed.
It is important to consider the cumulative effect of SWMPs on the watershed/subwatershed. While these SWMPs are designed to reduce sediment and contaminant impacts from urban runoff, they may alter the water balance or flow regime of water courses. Current practice seeks to more closely maintain the natural hydrology of developing areas through the use of lot level controls to promote infiltration. This is a goal, however, and is very difficult to be completely achieved. The effect of extended discharge on flows, erosion thresholds, and water levels – as they affect aquatic life or wetlands, must be accounted for in developing the watershed/ subwatershed plan.
Evaluation and assessment of alternative plans are based on predictions made by forecasting tools. Forecasts are needed for a variety of issues in a subwatershed, including flood evaluation, erosion evaluation, water balance and low flow modelling, groundwater quantity and quality, surface water quality, and ecological assessments. Tools for forecasting flooding are commonly used, and their forecasts readily accepted by professionals and the regulatory community. In fact, tools for addressing water quantity (flooding, low flow, groundwater flow) issues are much more advanced and in wider use than tools for ecological analysis. This SWM Planning and Design Manual has provided an updated methodology (see Chapter 3 and Appendix B) for assessing stream erosion and the effectiveness of management methods, but there remain uncertainties with the methodology which can only be addressed through monitoring studies.
A primary focus of watershed/subwatershed planning is to maintain or improve the ecological health of the watershed as land use change occurs. As a result, it is necessary to evaluate the impacts to the physical system and indicators in terms of their resulting impact on biological systems. The methods used to conduct this assessment range from the use of professional judgment and literature, to the use of empirical models. In the assessment of the mitigating measures to enhance habitat or protect ecosystems, the assessment may be even more based on professional judgment, due to the lack of recognized models or objective field data-sets which document the degree of protection provided.
In most watersheds or subwatersheds, there is a limit to which urban development and growth can proceed without causing irreparable damage to natural systems which support the watershed ecosystem. The threshold at which such damage may occur is variable and largely depends on the physical and biological characteristics of the area. The identification and protection of constraint areas and the mitigative measures specified as a part of the criteria to govern development, are methods of extending the development threshold by maximizing the protection provided to the key elements of the watershed. In some instances, however, there may be a need to further limit the cumulative impact of urban development by limiting the levels of imperviousness that are allowable.
In such areas, there are a variety of options ranging from control of development form (e.g., higher density, clustered and buffered development) to complete restriction of portions of the watershed/subwatershed to uses which do not produce a significant change in the hydrologic or hydrogeologic regimes of the watershed. The selection of the appropriate approach is not solely a watershed/subwatershed planning concern, but rather may require an in-depth assessment of the land use needs of the community. It is incumbent upon the watershed/ subwatershed plan to identify the concerns for cumulative impact, to identify the areas which could be subject to land use restrictions and to identify the levels of imperviousness which would be acceptable to avoid undesirable impacts. The watershed/subwatershed plan is not intended to set land use policy but to set the environmental factors to be met by future land use decisions.
![]()