Technical Update
Risk Assessment: Transition Process from the “Guideline for
Use at Contaminated Sites in Ontario” to the “Record of Site
Condition Regulation”
1. General Information
· The purpose of this update is to provide general information regarding the transition from
the Site Specific Risk Assessment (SSRA) acknowledgement under the Guideline for Use at Contaminates
Sites in Ontario (the Guideline) to the acceptance of risk assessments under the Record of Site Condition
Regulation (Regulation) under the Environmental Protection Act (EPA). The Regulation itself should
be consulted for the requirements to be met when it comes into force.
- The Regulation and related legislation will come into force on October 1, 2004.
- The
Regulation encompasses the requirements of the Guideline and builds upon them to provide a clearer
more transparent process.
- Under the Guideline, the date of submission of a risk assessment
refers to the date of the most recent submission or re-submission in response to MOE review
comments. A risk assessment is considered
under review by MOE from the most recent date of submission until the date MOE provides a response.
2. Transition of SSRAs under review by MOE Prior to June 17, 2004
- A SSRA that was under review prior to June 17, 2004, will be assessed by the MOE according
to the Guideline process before October 1, 2004.
- A SSRA which MOE acknowledges as satisfactory
under the Guideline process before October 1, 2004 is deemed to be a Risk Assessment that has
been accepted under the Regulation for the purpose
of filing a Record of Site Condition.
- A SSRA which has been or will be returned to the
proponent with MOE comments that the risk assessment is, in the opinion of the Ministry, unsatisfactory
under the Guideline process before October
1, 2004 must meet the requirements of the new Regulation when it is re-submitted.
3. Transition of SSRAs Submitted Between June 17 and July 9, 2004
- For all SSRA submissions received prior to July 9, 2004, the MOE will make every effort to
complete a review under the Guideline process prior to October 1, 2004.
- Depending upon the complexity of the submission, and the number of other SSRAs to be reviewed
that preceded the submission, SSRAs submitted between June 17, 2004 and July 9, 2004 may not receive
comment or acknowledgement from the MOE by October 1, 2004.
- For this reason, it is strongly
recommended that any SSRA submitted after June 17, 2004 but before July 9, 2004 meet the requirements
of Section 4 of Schedule C of the Regulation. These risk
assessments do not have to satisfy the other requirements of Schedule C such as the requirements
for pre-submission form (PSF) in Section 3 of Schedule C or certification statements set out in
Section
5.
- A SSRA which MOE acknowledges as satisfactory under the Guideline process before October
1, 2004 is deemed to be a Risk Assessment that has been accepted under the Regulation for the purpose
of filing a Record of Site Condition.
- A SSRA which has been or will be returned to the
proponent before October 1, 2004 with an indication that in the opinion of the Ministry the
risk assessment is unsatisfactory under the Guideline
process must meet the requirements of the new Regulation when it is re-submitted.
4. Transition of SSRAs Submitted Between July 9 and October 1, 2004
· As it is unlikely that MOE will be able to review this SSRA before October 1, 2004, a SSRA
submitted between July 9, 2004, and October 1, 2004 should meet the requirements of Section 4 of Schedule
C of the Regulation. Part B of this update explains the steps necessary to meet the requirements of
Section 4 of Schedule C of the Regulation.
- Risk Assessments do not have to include requirements of other sections of Schedule C such
as the PSF or certification statements, if they are submitted prior to October 1, 2004.
5. Transition of Risk Assessments Commenced before October 1, 2004, but Submitted After October 1,
2004
- Special provisions are in place for Risk Assessments which are commenced before October 1,
2004 but are not completed and submitted until after October 1 (including the date of the most
recent resubmission of previously reviewed SSRA or Risk Assessments).
- A Risk Assessment that was
commenced before October 1, 2004, but that was not submitted by October 1, 2004 must meet the
requirements of Section 44 of the Regulation. Section 44 states that:
- work completed before October
1, 2004 must be reviewed by a qualified person and that person must certify in writing (in
the form of an appendix) that the components of the SSRA meet the requirements
of the new Regulation, except that they were not completed by a qualified person; and,
- any
components that are required under Schedule C of the new Regulation that were not completed
when this Regulation came into force, must be completed by a qualified person and submitted
in accordance with the new Regulation.
- All risk assessments submitted after October 1, 2004 must include a PSF and all other requirements
of the Regulation. MOE will make the appropriate forms available in July 2004 and the MOE will begin
to review PSF’s no later than October 1, 2004.
6. Risk Assessments Commenced After October 1, 2004
- As of October 1, 2004, under the Regulation, the date of submission of a risk assessment
will be the date at which the timeline starts accordingto the provisions of the Regulation.
- Risk
Assessments commenced and submitted after October 1, 2004 are expected to meet all requirements
of the Regulation.
7. Transition for Re-submissions
- After July 9, 2004 all re-submissions including responses to reviewer comments should be
in accordance with Section 4 of Schedule C of the Regulation to be eligible for the provisions
of the Regulation if approved by MOE after October 1, 2004.
- After October 1, 2004 all re-submissions
must be in accordance with the new Regulation to be eligible for the provisions of the Regulation.
Part B – Meeting Section 4 of Schedule C of the Regulation
Section 4 of Schedule C requires risk assessments to meet the minimum requirements in Table 1 of Schedule
C. This includes laying out both the human health and ecological risk assessment reports under one
cover with sections and sub-headings as prescribed in Table 1 of Schedule C. The majority of the information
to be provided will be the same as required in the Guideline process. The purpose of prescribing a
consistent format for all risk assessments is to streamline the risk assessment review process in
order to meet regulatory timelines for review, beginning October 1, 2004.
Schedule C also covers estimation of local background concentrations, which comes under the heading
‘alternative risk assessment procedures’, so that it may provide an alternative to the prescribed
site condition standards as it did under the Guideline process. Estimation of local background concentrations
is predominantly a sampling procedure, however, and is exempted from the human health and ecological
risk assessment reporting requirements of Table 1 of Schedule C.
Information required under the Regulation which was not specifically required under the Guideline
process includes:
- The proposal of a standard (a numeric concentration of a contaminant) specified in the risk
assessment as a property-specific standard for each contaminant identified by the Qualified Person
who did the environmental site assessment(s) as a contaminant of concern.
- A pre-submission
form (PSF) submitted under Section 3 (for risk assessments submitted after October 1 2004) describing
the conceptual site model, self-declaration of the qualifications of the
Qualified Person for risk assessment and the type of risk assessment being submitted to which Section
46 of the Regulation applies.
- The inclusion in the exposure assessment calculations of
all potential exposure pathways, with and without risk management assumptions.
- A description
of the expertise required to undertake the risk assessment, the qualifications, including
the resumes, for the qualified person and technical leads and their role in preparing the
risk assessment report, and justification for the omission of expertise normally associated with
risk assessment.
- A summary of the phase one and two sampling programs, specifically considering
data quality, uncertainty and suitability of the data for use in the risk assessment.
- Details
of any additional sampling undertaken to support the risk assessment.
- If the risk
assessment will assume the ground water under the RA property does not or will not serve
as a raw water supply for a drinking-water system, as defined in the Safe Drinking Water
Act, 2002, provide a copy of the notification to local government, and the response provided from
the local government.
- Additional specific and enforceable detail in the description of
risk management performance objectives and proposed risk management measures, including requirements
for monitoring, maintenance,
replacement and contingency planning.
- Detailed plans and specifications of any proposed
engineering or hydrogeological controls, duly stamped by an appropriate person.
Changes from the Guideline process:
- Schedule C is more explicit in the assessment of off-site risk
than was the case under the Guideline process. Schedule C requires
an assessment of whether the property specific standard being proposed
in the risk assessment is likely to result in a concentration greater
than the applicable full depth site condition standard at the nearest
receptor located off-site. Where the applicable full depth site
condition standard is expected to be exceeded at a point of offsite
impact, the location and type of receptor which may be impacted
must be specified.
- If the property-specific standard proposed by the risk assessment
for groundwater is greater than 50% solubility, the requirement
for risk management measures (Level 2 risk management under the
Guideline) will not automatically be assumed but will be property-specific
based on a demonstration of the risk of free product formation and
the need for mitigation.
- Public communication is required where the risk assessment has
been identified by the Ministry as being located in an area where
multiple sites are affected by contaminant plumes including one
or more sites of origin (Wider Area of Abatement) (for risk assessments
submitted after October 1, 2004).
Contacts:
Mark Turner
Coordinator –Risk Assessment
Standards Development Branch
Tel: (416) 327-6949
Tim Krsul
Program Coordinator
Central Region ADO
Tel: (416) 326-4840
If you are having difficulty accessing a document, please contact the Ministry of the Environment
at picemail@ene.gov.on.ca or phone the ministry's Public
Information Centre at 1- 800-565-4923, in Toronto 416-325-4000 or by mail to the Ministry of the Environment,
Public Information Centre, 135 St. Clair Ave. West, 1st Floor, Toronto, ON. M4V 1P5.