Air page banner
 Location: Ministry Home > Publications > Technical Studies and Reports > 4022e4.pdf > HTML version

This is a HTML version of the original PDF document. The HTML version is being provided for reading purposes only and is not the official version of the document.

4. PREDICTIVE WATER AND SEDIMENT QUALITY MODEL

4.1 Objective

The objective of this component was to construct a water and sediment quality model to assess the level of cleanup required at the Deloro Mine Site for downstream arsenic, cobalt and nickel concentrations to reach, or fall below, provincial water and sediment quality objectives for the protection of aquatic life. In this exercise, the interim provincial water quality objective (PWQO of 5 µg/L (MOE 1999) was used for arsenic because the MOE has stated that one of the objectives of the final cleanup plan for the Deloro Mine Site is to meet this interim PWQO.

4.2 Scope

The Moira River Model (MRM) was built to simulate long-term water and sediment quality in the Moira River system between the Deloro Mine Site and the outlet of Stoco Lake. The model was based on average, long-term monthly water flows. The model incorporated sediment - water interaction and was calibrated to reflect general, long-term, water quality trends observed over the last 10 years. As such, the model may not adequately reflect the effects of short-term, sporadic events, such as flooding events, dry spells, or the effects of spring and fall turnover in lakes. However, the model included all of the most important processes that control long-term average metal concentrations in the Moira River system. The model was developed as a decision tool, and predictions are meant to serve as general indicators of the response of the Moira River system to future cleanup actions at the Deloro Mine Site.

4.3 Approach

The Moira River system between the Deloro Mine Site and the outlet of Stoco Lake was divided into nine model segments (Figure 4.3-1):

  • Deloro Mine Site to Young's Creek;
  • Young's Creek to half way to Bend Bay;
  • Remaining distance to Bend Bay;
  • Bend Bay;
  • Bend Bay to West Moira Lake;.
  • West Moira Lake;
  • East Moira Lake;
  • East Moira Lake to Stoco Lake; and
  • Stoco Lake.

RIVER SEGMENTS FOR WATER AND SEDIMENT QUALITY MODEL

REFERENCE
BASE MAP PROVIDED BY GIS GOLDER MISSISSAUGA

SCHEMATIC ONLY NOT TO SCALE

The MRM was built using STELLA software (HPS 1997). Each model segment incorporates advective transport, chemical partitioning, sediment deposition and resuspension, sediment bioturbation and sediment burial (Figure 4.3-2). The MRM was calibrated using historical water flow and water quality data and results from recent sediment sampling (as described in Section 2.2). Calibration also included adapting partition, deposition, burial and resuspension rates taken from relevant, available literature. The calibrated MRM was then used to determine the level of cleanup required at the Deloro Mine Site for downstream arsenic, cobalt and nickel concentrations to reach, or fall below, provincial water quality objectives (PWQOs) for the protection of aquatic life.

Arsenic, cobalt and nickel were selected from the metals of concern discussed in Sections 2.1 and 2.2, because:

  • arsenic and cobalt concentrations consistently exceeded PWQOs throughout the Moira River system; and,
  • other heavy metals, including silver, copper and lead, will exhibit similar behavioural patterns as one of the chosen substances (i.e., in-stream concentrations will increase or decrease in the same fashion as predicted for one of the modelled substances).

Figure 4.3-2
Illustration of the Pathways Included in the Moira River Model

4.4 Model Construction and Calibration

The general set-up of the MRM is described in Section 4.4.1, followed by a discussion of how water flows and the movement of suspended sediments were incorporated into the MRM (Sections 4.4.2 and 4.4.3, respectively). Section 4.4.4 describes the chemical component of the MRM in greater detail and the general process used to calibrate the model for arsenic, cobalt and nickel.

4.4.1 Model Set-up

The physical dimensions of each of the nine model segments are summarized in Table 4.4-1. Each model segment was sub-divided into three compartments: water, surface sediment (the uppermost 10 cm of the sediment profile) and deep sediment (below a sediment depth of 10 cm). The water compartment in each model segment was assumed to be completely mixed, an assumption supported by the absence of thermal stratification in Moira and Stoco lakes (Section 2.1). Surface sediments were also assumed to be completely mixed to a depth of 10 cm to account for bioturbation by benthic invertebrates (Diamond 1995, Bosworth and Thibodeaux 1990). The deep sediments do not mix in the model; they act as a sink for buried sediment and associated heavy metals (Figure 4.3-2).

Table 4.4-1
The Physical Dimensions of Each Model Segment

SegmentDepth (m)Width (m) Surface Area (m2)Volume (m3)Source
NumberName
1Deloro to Young's Creek130114 000114 000 Based on data from Section 2.3
2Young's Creek to half way to Bend Bay130 186 000186 000Based on datafrom Section 2.3
3Remaining distance to Bend Bay130214 500214 500 Based on data from Section 2.3
4Bend Bay1-210 000210 000Diamond (1995)
5Bend Bay to West Moira Lake130102 000102 000 Based on data from Section 2.3
6West Moira Lake3.5-2 160 0007 560 000 Diamond (1995)
7East Moira Lake (EML)4-6 110 00024 440 000 Diamond (1995)
8EML to Stoco Lake250890 0001 780 000 Based on data from Section 2.3
9Stoco Lake4-5 630 00022 520 000 MOE (1972, 1974)

The concentration of arsenic, cobalt or nickel in the water compartment of a given model segment was calculated based on the following relationship:

concentration at time "t" = mass at time "t" / water volume at time "t"

where,

mass at time "t" = mass at time "t-1" + the change in mass from time "t-1" to time "t" (Δm)

and,

Δm = mass in - mass out - mass settled + mass resuspended + mass diffused

Similarly, arsenic, cobalt or nickel levels in the surface sediments of a given model segment were calculated based on the same relationship where:

concentration at time "t" = mass at time "t" / sediment volume at time "t"

and,

Δm = mass settled - mass resuspended - mass diffused - mass buried

The chemical mass moving in and out of each model segment was controlled by water flow. Sediment interactions (i.e., settling, resuspension and burial) were controlled, in part, by the rates at which sediments settled, became resuspended or were buried. Sediment settling, resuspension and burial rates operated independently from the chemical being modelled (i.e., they were the same for arsenic, cobalt and nickel).

4.4.2 Water Flows

Source Data

The sources of the water flow data used in the MRM are given in Table 4.4-2. Monthly precipitation data from 1925 to 1990 were taken from an Environment Canada monitoring station located in Tweed, Ontario (Environment Canada 1994). Estimates of monthly evapotranspiration rates were derived from MOE (1974). Average, monthly net precipitation rates used in the MRM are illustrated in Figure 4.4-1.

Table 4.4-2
Source of Water Flow Data Used to Build the Moira River Model

WaterbodyStation NumberData Available Sourcea
Moira River – at Deloro02HL005Continuous monthly data from 1966 to 19981, 2
– at Thomasburg02HL104Monthly data from 1969 to 19701
– at Foxboro02HL001Continuous monthly data from 1965 to 19981, 2
Young's CreekEstimate of average annual flow3
Black River02HL003Continuous monthly data from 1955 to 19951
Skootamatta River02HL004Continuous monthly data from 1955 to 19951
Clare River02HL102Monthly data from 1968 to 19771

a1 = Environment Canada (1999), 2 = WSC (2000) and 3 = CG&S (1999).

Figure 4.4-1
Average, Monthly Net Precipitation Rates Used in the Moira River Model

Water Balance

The long-term water balance for the Moira River system was constructed based on the assumption that the volume of water held within each model segment was constant over time. Therefore,

segment outflow = upstream inflow + tributary inflow + net precipitation

Tributaries included in the model were: the Black and Skootamatta rivers (discharging to the Moira River between Moira and Stoco lakes); the Clare River (discharging to Stoco Lake); Young's Creek (discharging to the Moira River downstream of Highway 7); and, Madoc Creek (discharging to West Moira Lake).

Long-term, average monthly flow rates were calculated for the Black, Skootamatta and Clare rivers and for the Moira River at Deloro. For Young's Creek, the average annual flow rate calculated by CG&S (1999) was equivalent to 0.2% of the long-term, average annual flow rate observed in the Moira River at Deloro, so monthly flows in Young's Creek were assumed to be equal to 0.2% of monthly flows observed in the Moira River at Deloro. Similarly, Diamond (1995) noted that flows in Madoc Creek, a small tributary to West Moira Lake, were approximately equal to 10% of the inflow from the Moira River, so monthly flows in Madoc Creek were assumed to be equal to 10% of monthly flows in the Moira River at the inlet to West Moira Lake.

Net precipitation, as defined in Figure 4.4-1, was included in the Bend Bay, West Moira Lake, East Moira Lake and Stoco Lake model segments, but it was not included (i.e., set to zero) in the five river segments. It was assumed that evaporation and precipitation would only be significant in large open water areas with relatively still waters. The gain or loss of water through evaporation and precipitation represented a small fraction of the water flowing through each lake segment (Table 4.4-3), and the inclusion of net precipitation in the river segments would not substantially alter the conclusions of this study.

To calibrate the water balance, monthly outflows from the Stoco Lake model segment were compared to average monthly flow rates recorded at the Thomasburg monitoring station. Only two years worth of data were available from the Thomasburg monitoring station (Table 4.4-2). To increase the amount of data available for comparison, data from the Foxboro monitoring site were transformed using the following relationship:

QTx = QFx * ((QFa - QTa) / QFa)

where: QTx = monthly flow at Thomasburg in Year "x" (m3/s)

QFx = monthly flow at Foxboro in Year "x" (m3/s)

QFa = average monthly flow at Foxboro between 1969 and 1970 (m3/s)

QTa = average monthly flow at Thomasburg between 1969 and 1970 (m3/s)

Stream flows in Clare River were adjusted until the outflow from Stoco Lake matched with the average monthly flow record developed for Thomasburg. The resulting water balance is summarized in Table 4.4-3.

Table 4.4-3
Water Flow Through The Moira River Model

Model SegmentParameterMonth
JanFebMarAprilMayJune JulyAugSeptOct NovDec
Deloro to Young's CreekUpstream inflow (m3/s)3.53.07.714.35.2 1.70.60.30.61.33.54.2
Outflow (m3/s)3.53.07.714.35.21.70.60.30.6 1.33.54.2
Retention time (day)0.40.40.20.10.30.82.34.72.1 1.00.40.3
 
Young's Creek to half way to Bend BayUpstream inflow (m3/s)3.5 3.07.714.35.21.70.60.30.6 1.33.54.2
Young's Creek (m3/s)0.0070.0060.0160.0290.0110.0040.001 0.0010.0010.0030.0070.009
Outflow (m3/s)3.53.07.714.35.31.80.60.30.6 1.33.54.2
Retention time (day)0.60.70.30.20.41.23.77.73.4 1.60.60.5
 
Remaining distance to Bend BayUpstream inflow (m3/s)3.53.07.714.3 5.31.80.60.30.61.33.54.2
Outflow (m3/s)3.53.07.714.35.31.80.60.30.6 1.33.54.2
Retention time (day)0.70.80.30.20.51.44.38.83.9 1.90.70.6
 
BendBayUpstream inflow (m3/s)3.53.07.714.35.31.8 0.60.30.61.33.54.2
Net precipitation (m3/s)0.0060.0040.0030.001-0.001-0.002-0.004 -0.0020.0040.0030.0050.006
Outflow (m3/s)3.53.07.714.35.31.70.60.30.6 1.33.54.2
Retention time (day)0.70.80.30.20.51.44.38.73.8 1.80.70.6
 
Bend Bay to West Moira LakeUpstream inflow (m3/s)3.53.07.714.3 5.31.70.60.30.61.33.54.2
Outflow (m3/s)3.53.07.714.35.31.70.60.30.6 1.33.54.2
Retention time (day)0.30.40.20.10.20.72.14.21.8 0.90.30.3
 
West Moira LakeUpstream inflow (m3/s)3.53.07.714.35.3 1.70.60.30.61.33.54.2
Madoc Creek (m3/s)0.350.300.771.430.530.170.060.03 0.060.130.350.42
Net precipitation (m3 /s)0.060.050.030.01-0.01 -0.02-0.04-0.030.040.030.060.06
Outflow (m3/s)4.03.48.615.75.81.90.60.30.7 1.53.94.7
Retention time (day)22261061546149311117 592219
 
East Moira Lake (EML)Upstream inflow (m3/s)4.03.48.615.75.8 1.90.60.30.71.5 3.94.7
Net precipitation (m3/s)0.160.130.090.03-0.03-0.07-0.11-0.07 0.110.100.160.18
Outflow (m3/s)4.13.58.615.85.71.80.50.20.9 1.64.14.8
Retention time (day)69813318491545991346331 1787058
 
EML to Stoco LakeUpstream inflow (m3/s)4.13.58.615.85.7 1.80.50.20.91.64.14.8
Black River (m3/s)4.43.69.317.77.32.81.41.31.4 1.94.35.4
Skootamatta River (m3/s)7.67.015.330.012.54.11.51.0 1.53.16.99.1
Outflow (m3/s)16.114.033.363.425.58.73.42.53.8 6.615.219.4
Retention time (day)1.31.50.60.30.82.46.18.25.5 3.11.41.1
 
Stoco LakeUpstream inflow (m3/s)16.114.033.363.425.58.7 3.42.53.86.615.219.4
Clare River (m3/s)9.08.918.733.113.82.50.40.30.2 0.31.32.4
Net precipitation (m3 /s)0.150.120.080.03-0.03-0.06-0.11-0.07 0.100.090.150.17
Outflow (m3/s)25.323.152.196.639.311.13.72.74.0 7.016.721.9
Retention time (day)10115372471956537 1612

4.4.3 Suspended Solids

Source Data

The turbidity and total suspended solids (TSS) data used to calibrate the MRM were obtained from a series of water quality sample stations maintained by the Ontario Ministry of the Environment (see Section 2.1). TSS monitoring has been limited to occasional sampling since 1998. Turbidity measurements are available from 1967 to the end of 1998. Using the available TSS information, a turbidity to TSS relationship was developed (Figure 4.4-2). Long-term, average annual turbidity levels were transformed into TSS concentrations using this relationship (Table 4.4-4). The resulting annual average TSS concentration for West Moira Lake (i.e., 3.9 mg/L) matched the annual average TSS concentration reported by Diamond (1995).

Figure 4.4-2
Total Suspended Solids Concentrations in the Moira River System as a Function of Turbidity
as a Function of Turbidity

Table 4.4-4
Average Annual Total Suspended Solids and Turbidity Levels in the Moira River System

WaterbodyTurbidity (NTU)Total Suspended Solids
Measured (mg/L)Deriveda(mg/L)
Moira River - upstream of Deloro2.03.2
- upstream of Young's Creek2.52.23.6
- between East Moira and Stoco lakes2.32.43.5
Madoc Creek3.42.84.5
Black River1.92.23.2
Skootamatta River2.22.23.4
Clare River3.04.04.1
West Moira Lake2.83.33.9
Stoco Lake3.83.54.8

a Derived based on the relationship illustrated in Figure 4.4-2.
- = no data.

Sediment Balance

A sediment mass balance for the Moira River system was constructed based on the assumption that sediment density, sediment porosity, the depth of the surface sediment layer and the amount of suspended sediment contained within each model segment were constant over time. Under these conditions,

outgoing sediment mass = total incoming sediment mass - buried sediment mass

or

Qout* [TSS] = Qin*[TSS]in - Vb*A*(1-φ)*ρ*C

where: Qout = outflow from model segment "x" (m3/s)

[TSS] = TSS concentration in model segment "x" (mg/L)

Qin = inflow to model segment "x" (m3/s)

[TSS]in= TSS concentration in segment "x" inflow (mg/L)

Vb= burial velocity (mm/yr)

A = active sediment area (m2)

φ = sediment porosity (unitless)

ρ = sediment density (kg/L)

C = unit conversion factor

Each parameter listed above was assigned a value based on available literature. The rate at which sediments were buried (Vb) and the initial TSS concentration in each segment ([TSS]) were then adjusted to achieve a balance. Values assigned to each parameter are listed in Table 4.4-5, and the resulting sediment balance is summarized in Table 4.4-6.

Table 4.4-5
Values Used to Achieve a Sediment Balance for the Moira River System

Model SegmentSedimentTSS Active Sediment Areaa(%)Burial Velocity
Density (kg/L)Porosity (unitless)Initial (mg/L)Final (mg/L)Initial mm/yr) Final (mm/yr)
Deloro to Young's Creek2.2b0.98cd 3.6e3.620f0.236f0.205
Young's Creek to half way to Bend Bay3.6e3.620f0.236f 0.207
Remaining distance to Bend Bay3.6f3.620f0.236f 0.218
Bend Bay3.5b3.580b1.180f1.314
Bend Bay to West Moira Lake3.5f3.520f0.236f0.202
West Moira Lake3.9b3.133b2.360c2.054
East Moira Lake (EML)3.9b2.033b3.530d1.618
EML to Stoco Lake3.5e3.025f1.765f1.811
Stoco Lake4.8e2.933f3.530f3.524

aActive sediment area = fraction of bottom area where sediment accumulates.

bBased on information from Diamond (1995).

cBased on information from Mudroch and Capobianco (1980).

dBased on information from Cornett et al. (1987).

eBased on information in Table 4.4-4.

fAssumed value based on the characteristics of the other model segments.

Sediment Settling and Resuspension

For sediment density, sediment porosity and the depth of the surface sediment layer to be constant over time within each model segment,

resuspended sediment mass = settled sediment mass – buried sediment mass

or,

Vr*A*(1- φ )*ρ = Vs*A*[TSS]*C - Vb*A*(1- φ)*ρ

where: Vr = resuspension velocity (mm/yr)

Table 4.4-6
Sediment Balance for the Moira River System

Model SegmentParameterMonth (kg/month)
JanFebMarAprilMayJune JulyAugSeptOctNovDec
Deloro to Young's CreekUpstream sediment 34018264117430013269450946 16468558127155938127053256240213
Buried sediment1612356324831361519
Outgoing sediment340022639974265132631509221646055782714593612699 3254640194
 
Young's Creek to half way to Bend Bay Upstream sediment340022639974265132631 5092216460557827145936126993254640194
Young's Creek69541522711043411612266682
Buried sediment2721581044013425102531
Outgoing sediment3404526432743591327985098616481558527175943 127153258740244
 
Remaining Bay distance to Bend Upstream sediment 34045264327435913279850986 16481558527175943127153258740244
Buried sediment3225701264816536123138
Outgoing sediment340122640774289132672509381646555802715593712703 3255740206
 
Bend BayUpstream sediment34012264077428913267250938164655580 27155937127033255740206
Buried sediment724566166930231173 39716485101259695860
Outgoing sediment332882584172620129650497651606854152630583612444 3186239346
 
Bend Bay to West Moira Lake Upstream sediment33288 258417262012965049765160685415 26305836124443186239346
Buried sediment1411315521 721251417
Outgoing sediment332742583072589129594 4974416062541326295834124383184839329
 
West Moira LakeUpstream sediment3327425830 72589129594497441606254132629 5834124383184839329
Madoc Creek sediment 426833139310166226380 2060694337748159540855044
Buried sediment4721369511083201757854 26991181620597166145285617
Outgoing sediment328212544870816126041 4827015422492623465985123733140538756
 
East Moira Lake (EML)Upstream sediment3282125448 70816126041482701542249262346 5985123733140538756
Buried sediment107688404246444456917269 581623601213154938731032112782
Outgoing sediment2205317044461738147231000 960625661133443785002108325974
 
EML to Stoco LakeUpstream sediment2205317044 461738147231000960625661133 443785002108325974
Black River sediment37880279447986414646362735 23341118301097411563160693534246703
Skootamatta R. sediment6930058058139232263762 114505361351395092761323028350 6075282833
Buried sediment7911085955437239561589 13701412353618-21235
Outgoing sediment128442101961264313487326 2042856749426976199702887852300117179154274
 
Stoco LakeUpstream sediment128442101961 2643134873262042856749426976199702887852300117179154274
Clare River sediment9856889187204317351150153033268174472335916643695 1419025843
Buried sediment27995254165982010406245552873523661668-168734085 7556
Outgoing sediment199014165733408809734414 3117668557629082216613055855123 127285172560

A = active sediment area (m2).

φ = sediment porosity (unitless)

ρ = sediment density (kg/L)

Vs = settling velocity (mm/yr)

[TSS] = TSS concentration (mg/L)

C = unit conversion factor

Vb = burial velocity (mm/yr)

All of these parameters, except for resuspension and settling velocity, have been defined by the sediment balance described above (Table 4.4-5). Settling velocities (Vs) were initially derived from sedimentation rates and TSS concentrations reported by Diamond (1995) using the following relationship:

settling velocity (m/yr) = sedimentation rate (g/m2/yr) / TSS concentration (g/m3)

The resulting values were then scaled to reflect the changes in burial velocity required to achieve a sediment balance (i.e., final settling velocity = initial settling velocity * final burial velocity / initial burial velocity) (Table 4.4-7). The new settling rates were plugged back into Equation (9) to produce the corresponding resuspension velocities listed in Table 4.4-7.

Table 4.4-7
Settling and Resuspension Rates in the Moira River System

Model SegmentSettling VelocityResuspension Velocity (mm/yr)
Initial (mm/yr)Final (mm/yr)
Deloro to Young's Creek28077a243351.79
Young's Creek to half way to Bend Bay28077a246471.81
Remaining distance to Bend Bay28077a259201.90
Bend Bay140385a15637611.2
Bend Bay to West Moira Lake28077a240601.72
West Moira Lake280769b24440715.2
East Moira Lake (EML)121667b557760.92
EML to Stoco Lake60834a624322.40
Stoco Lake121667a1214744.59

aAssumed value based on settling velocities in East and West Moira Lake.
bBased on information from Diamond (1995).

4.4.4 Selected Metals of Concern

Model Equations

As stated in Section 4.4.1, the change in mass of arsenic, cobalt or nickel in the water compartment of a given model segment was calculated based on the following relationship:

Δmwater = mass in - mass out - mass settled + mass resuspended + mass diffused

or,

Δmwater = Qin*[metal]in - Qout*[metal] - Vs*A*Fpw*[metal]*C + Vr*A*[metal]sed*C +
VD*A* (Fds*[metal]sed - Fdw*[metal])*C

where: Qin = inflow to model segment "x" (m3/s)

[metal]in = total concentration of metal "z" in inflow to model segment "x" (µg/L)

Qout = outflow from model segment "x" (m3/s)

[metal] = total concentration of metal "z" in model segment "x"(µg/L)

Vs = settling velocity (mm/yr)

A = active sediment area (m2)

Fpw = fraction of metal "z" associated with suspended sediment (unitless)

Vr = resuspension velocity (mm/yr)

metal]sed = total concentration of metal "z" in model segment "x" sediment (µg/L)

C = unit conversion factor

VD = diffusion velocity (mm/yr)

Fds = fraction of metal "z" dissolved in porewater (unitless)

Fdw = fraction of metal "z" dissolved in water (unitless)

Changes in the mass of arsenic, cobalt or nickel contained in surface sediments were calculated using a similar relationship:

Δmsed = mass settled - mass resuspended - mass diffused - mass buried

or,

Δmsed = Vs*A*Fpw*[metal] – Vr*A*[metal]sed – VD*A*(Fds*[metal]sed – Fdw*[metal])*C –
Vb*A*[metal]sed

where: Vb = burial velocity (mm/yr)

Flow rates (Q), burial velocities (Vb), settling velocities (Vs), resuspension velocities (Vs) and active sediment areas (A) for each model segment have been defined through the water and sediment balances discussed in Sections 4.4.2 and 4.4.3, respectively. The remaining parameters were defined as follows:

Diffusion velocities (VD) for arsenic, cobalt and nickel were derived using the following formula (Chapra 1997):

VD = 69.35 * φ * MWion2/3

where: φ = sediment porosity (unitless)

MWion = molecular weight of the dominant ion (g/mol)

The dominant ionic form for arsenic, cobalt and nickel were assumed to be H2AsO4 (Cornett et al. 1987), Co and Ni (Cornett et al. 1987), respectively.

The fraction of chemical dissolved in water (Fdw) was defined as:

Fdw = 1/ (1 + Kw* [TSS])

where: Kw = partition coefficient for water (L/mg)

[TSS] = concentration of total suspended solids (mg/L)

Fpw = 1 -Fdw

The fraction of chemical dissolved in sediment porewater (Fds) was defined as:

Fds = 1/ (1 + Ks* (1-φ) * ρ)

where: Ks = partition coefficient for sediment (L/g)

φ = sediment porosity (unitless)

ρ = sediment density (kg/L)

Tributary and Upstream Input

Young's Creek, Madoc Creek, the Black, Skootamatta and Clare rivers and the Moira River upstream of the Deloro Mine Site were assigned arsenic, cobalt and nickel concentrations based on average concentrations observed in each waterbody over the past 10 years (i.e., January 1990 to January 2000)

Table 4.4-8
Average Arsenic, Cobalt and Nickel Concentrations in Tributaries to the Moira River
and in the Moira River Upstream of the Deloro Mine Site (1990 to 2000)

WaterbodySample SiteaArsenic (µg/L)Cobalt (µg/L) Nickel (µ g/L)
Moira River – upstream of DeloroW11.00.72.3
Young's CreekDM1163.995.032.8
Madoc CreekW4 and W51.1 0.31.3
Black RiverW90.50.30.8
Skootamatta RiverW100.50.30.8
Clare RiverW12 and W130.80.32.0

aSample locations are shown on Figure 2.1-1.

Loading from the Deloro Mine Site

The amount of arsenic, cobalt and nickel reaching the Moira River at or near the Deloro Mine Site was determined by examining water quality results from the following monitoring stations:

  • W1 – at Malone upstream of Deloro;
  • W2 – at Highway 7 bridge downstream of Deloro;
  • DM7 – at Highway 7 bridge downstream of Deloro;
  • DM1 – on Young's Creek near confluence with Moira River; and,
  • DM8 – on Moira River immediately below confluence with Young's Creek.

Loading rates were calculated using mean annual concentrations for the past 10 years and average annual flow in Moira River recorded at Highway 7, as shown in Table 4.4-9.

Table 4.4-9
Loading Rates from the Deloro Mine Site to the Moira River

ParameterUnitsArsenicCobaltNickel
Between Deloro and Highway 7 - Deloro Mine Site
Water flowaUpstream of Delorom3/s4.18
Upstream of Young's Creekm3/s4.18
ConcentrationUpstream of Deloroµg/L1.00.72.3
Upstream of Young's Creekµg/L43.34.55.6
Loading ratesUpstream of Deolorokg/yr13293304
Upstream of Young's Creekkg/yr5713594739
Deloro Mine Sitekg/yr5581501435
Between Highway 7 and Downstream of Young's Creek - immediately below Deloro Mine Site
Water flowaUpstream of confluence with Young's Creekm3/s4.18
Young's Creekm3/s0.01
Downstream of confluence with Young's Creekm3/s4.19
ConcentrationUpstream of Young's Creekµg/L43.34.55.6
Young's Creekµg/L163.995.032.8
Downstream of confluence with Young's Creekµg/L52.129.68.7
Loading ratesUpstream of Young's Creek kg/yr5713594739
Young's Creekkg/yr41248
Downstream of Young's Creekkg/yr687539061148
Immediately below Deloro Mine Sitekg/yr11213288401

aAssuming that a negligible amount of water comes off the Deloro Mine Site.

Total estimated loading rates for the following contributing areas are summarized in Table 4.4-10:

  • upstream of the Deloro Mine Site
  • from Deloro Mine Site to Highway 7;
  • Golder Associates
  • Young's Creek; and,
  • from Highway 7 to below confluence with Young's Creek.

Estimated loading rates are similar to those calculated by CG&S (1999). As noted by CG&S (1999), there is a significant amount of arsenic, cobalt and nickel entering the Moira River between Highway 7 and the confluence of Young's Creek.

Table 4.4-10
Summary of Estimated Loading Rates (kg/yr) to the Moira River near the Deloro Mine Site

SourceArsenicCobaltNickel
Existing upstream load13293304
Between Deloro Mine Site and Highway 75581501435
Young's Creek41248
Between Highway 7 and Young's Creek11213288401
Total390668751148

Calibration Procedure

Based on information from Diamond (1990, 1995) and Cornett and Chant (1986), partition coefficients (Kw) for arsenic, cobalt and nickel in water were developed using the following equation:

Kw = (1 - [d. metal] / [t. metal]w) / ([d. metal] / [t. metal] w * [TSS])

where: [d. metal] = concentration of metal "z" dissolved in water (µg/L)

[t. metal]w = total concentration of metal "z" in water (µg/L)

[TSS] = concentration of total suspended solids (mg/L)

Sediment partition coefficients (Ks) were developed using information from Diamond (1990) and Azcue and Dixon (1994) in the equation:

Ks = (1 - [p.metal] / [t. metal]s) / ([p. metal] / [t. metal]s * (1-φ)* ρ)

where: [p. metal] = concentration of metal "z" in porewater (µg/L)

[t. metal]s = total concentration of metal "z" in surface sediments (µg/g)

φ = sediment porosity (unitless)

ρ = sediment density (kg/L)

Partition coefficients, diffusion velocities and initial water and sediment concentrations were then adjusted to calibrate the MRM, so that arsenic, cobalt and nickel concentrations predicted by the MRM matched trends observed in the river over the last 10 years. The calibration was performed under steady state conditions. It was deemed complete when the modelled concentrations in water reasonably reflected historical levels, and sediment concentrations were constant over time. Final parameter values used to calibrate the MRM are summarized in Tables 4.4-11 and 4.4-12, and results of the calibration are shown in Figures VI-1 to VI-24 (Appendix VI).

For arsenic and nickel, a good calibration was generally obtained in all model segments (Appendix VI, Figures VI-1 to VI-8 and VI-17 to VI-24). With cobalt, a good calibration was achieved in the five model segments upstream of West Moira Lake. The MRM consistently overestimated cobalt concentrations during the open water season in the remaining four model segments, suggesting that there may be an additional sink for cobalt that is not included in the MRM (e.g., uptake by growing vegetation).

Table 4.4-11
Partition Coefficients and Diffusion Velocities Used to Calibrate the Moira River Model

ChemicalPartition CoefficientDiffusion Velocity (mm/yr)
Water (L/mg)Porewater (L/g)
Arsenic0.0162.72.7
Cobalt

0.139a
0.070b

24.34.5
Nickel0.0990.184.5

aFrom Upstream of Deloro to the inlet of West Moira Lake.

bFrom West Moira Lake to the outlet of Stoco Lake.

Table 4.4-12
Initial Arsenic, Cobalt and Nickel Concentrations Used to Calibrate the Moira River Model

Model SegmentArsenicCobalt Nickel
Water (µg/L)Sediment (µg/L) Water (µg/L)Sediment (µg/L)Water (µg/L) Sediment (µg/L)
Deloro to Young's Creek43.33154.52145.6130
Young's Creek to half way to Bend Bay52.1380 10.34908.7210
Remaining distance to Bend Bay52.139010.35058.7220
Bend Bay52.170510.38958.7500
Bend Bay to West Moira Lake52.137010.34908.7200
West Moira Lake53.06509.84908.1490
East Moira Lake (EML)76.037513.330010.5225
EML to Stoco Lake 19.0 88 3.3 69 3.2 80
Stoco Lake 18.0 93 3.1 67 3.2 105

4.5 Model Implementation

Once calibrated, the MRM was used to: (1) predict arsenic, cobalt and nickel concentrations downstream of the Deloro Mine Site assuming that all loading from the Deloro Mine Site ceased; and, (2) determine the level of cleanup required on site for downstream arsenic, cobalt and nickel concentrations in water to reach, or fall below, PWQOs and provincial sediment quality guidelines (PSQGs) for the protection of aquatic life.

4.5.1 No Loading Scenarios

As a result of short retention times (Table 4.4-3), arsenic concentrations in the water column quickly dropped below the interim PWQO of 5 mg/L (MOE 1999) after all arsenic loading from the Deloro Mine Site, between Highway 7 and Young's Creek, and Young's Creek was eliminated (Table 4.4-13). The interim PWQO for arsenic of 5 µg/L was used for this component, because the MOE has stated that one of the objectives of the final cleanup plan for the Deloro Mine Site is to meet this interim PWQO. Arsenic concentrations in surface sediments remained above the Ontario sediment Severe Effect Level (SEL) guideline of 33 mg/g (MOE 1993) at all model segments for the first 10 years, then declined to less than the SEL in some portions of Moira Lake and Stoco Lake after 20 years

Table 4.4-13
Predicted Concentrations of Arsenic Downstream Assuming
No Arsenic Loading from Deloro Mine Site

Model Segment Initial After Provincial
Guidelinea
5 yrs 10 yrs 20 yrs 30 yrs
Water (µgL)bc
Deloro to Young's Creek 43.3 1.0 - 1.1 1.0 - 1.1 1.0 - 1.0 1.0 - 1.0 5.0
Young's Creek to half way to Bend Bay 52.1 1.0 - 1.2 1.0 - 1.2 1.0 - 1.1 1.0 - 1.1
Remaining distance to Bend Bay 52.1 1.0 - 1.4 1.0 - 1.3 1.0 - 1.2 1.0 - 1.1
Bend Bay 52.1 1.2 - 2.2 1.1 - 1.7 1.0 - 1.3 1.0 - 1.2
Bend Bay to West Moira Lake 52.1 1.3 - 2.3 1.3 - 2.3 1.0 - 1.3 1.0 - 1.2
West Moira Lake 53.0 2.0 - 2.8 1.4 - 1.8 1.1 - 1.2 1.0 - 1.1
East Moira Lake (EML) 76.0 2.4 - 3.4 1.7 - 2.4 1.2 - 1.7 1.1 - 1.4
EML to Stoco Lake 19.0 0.8 - 1.2 0.7 - 1.0 0.6 - 0.8 0.6 - 0.7
Stoco Lake 18.0 0.9 - 1.2 0.8 - 1.0 0.7 - 0.8 0.7 - 0.7
Sediment (µg/g)cd
Deloro to Young's Creek 315 243 196 129 88

6.0 (LEL)
33 (SEL)

Young's Creek to half way to Bend Bay 380 293 236 154 105
Remaining distance to Bend Bay 390 299 239 154 105
Bend Bay 705 299 149 44 21
Bend Bay to West Moira Lake 370 287 233 153 106
West Moira Lake 650 226 98 27 16
East Moira Lake (EML) 375 290 230 144 96
EML to Stoco Lake 88 64 48 28 18
Stoco Lake 93 58 38 19 12

aWater quality objective from MOE (1999); sediment quality guidelines from MOE (1993)

bConcentrations in water reported as minimum to maximum levels observed in Year 5, 10, 20 or 30.

cValues in bold exceed the PWQO or the Severe Effect Level (SEL) sediment guideline.

dSediment concentrations at the end of Year 5, 10, 20 or 30.

Cobalt concentrations in the water column decreased rapidly after loading from the Deloro Mine Site, Young's Creek and between Highway 7 and Young's Creek ceased (Table 4.4-14). However, up to 30 years after all loading to the river ceased, cobalt levels in Bend Bay and Moira Lake remained above the PWQO of 0.9 µg/L for at least part of the year. Cobalt concentrations in surface sediments were below screening level concentrations (SLC) in Moira and Stoco lakes 10 years after all cobalt loading to the Moira River ceased (Table 4.4-14). Sediment cobalt concentrations in all model segments were less than the SLC of 296 µg/g after 20 years.

Initial nickel concentrations in water in all model segments were below the PWQO of 25 µg/L (MOE 1999). They decreased to background levels after all nickel discharges from the Deloro Mine Site and adjacent areas, including Young's Creek stopped (Table 4.4-15). Surficial sediments initially contained nickel concentrations in excess of the provincial SEL guideline of 75 mg/g (MOE 1993). Nickel levels in the surface sediment exceeded the SEL in all model segments, except East Moira Lake to Stoco Lake, 10 years after nickel loading ceased. Nickel levels declined below the SEL in the Deloro to Young's Creek and Stoco Lake model segments after 20 years. They remained above the SEL in Bend Bay and Moira Lake even after 30 years.

Table 4.4-14
Predicted Concentrations of Cobalt Downstream Assuming
No Cobalt Loading from Deloro Mine Site

Model Segment Initial After Provincial
Guidelinea
5 yrs 10 yrs 20 yrs 30 yrs
Water (µgL)bc
Deloro to Young's Creek 4.5 0.7 – 0.7 0.7 - 0.7 0.7 - 0.7 0.7 - 0.7 0.9
Young's Creek to half way to Bend Bay 10.3 0.7 – 0.9 0.7 - 0.9 0.7 - 0.8 0.7 - 0.8
Remaining distance to Bend Bay 10.3 0.7 - 1.1 0.7 - 1.0 0.7 - 0.9 0.7 - 0.9
Bend Bay 10.3 1.0 - 2.1 0.8 - 1.5 0.7 - 1.1 0.7 - 1.0
Bend Bay to West Moira Lake 10.3 1.0 - 2.1 0.9 - 1.6 0.7 - 1.1 0.7 - 1.0
West Moira Lake 9.8 1.4 - 2.1 1.0 - 1.4 0.7 - 0.9 0.6 - 0.8
East Moira Lake (EML) 13.3 1.6 - 2.4 1.2 - 1.8 0.8 - 1.2 0.7 - 1.0
EML to Stoco Lake 3.3 0.2 - 0.6 0.2 - 0.5 0.1 - 0.3 0.1 - 0.3
Stoco Lake 3.1 0.3 - 0.6 0.2 - 0.4 0.1 - 0.3 0.1 - 0.2
Sediment (µg/g)cd
Deloro to Young's Creek214 174 147 107 83 296 (SLC)
Young's Creek to half way to Bend Bay 490 388 321 222 162
Remaining distance to Bend Bay 505 398 328 225 163
Bend Bay 895 425 243 104 70
Bend Bay to West Moira Lake 490 394 329 230 169
West Moira Lake 490 220 121 53 38
East Moira Lake (EML) 300 247 205 141 102
EML to Stoco Lake 69 54 42 27 18
Stoco Lake 67 45 32 17 11

a Water quality objective from MOE (1999); Screening Level Concentration (SLC) calculated according to MOE (1993).

bConcentrations in water reported as minimum to maximum levels observed in Year 5, 10, 20 or 30.

cValues in bold exceed he PWQO or the SLC.

dSediment concentrations at the end of Year 5, 10, 20 or 30.

Table 4.4-15
Predicted Concentrations of Nickel Downstream Assuming
No Nickel Loading from Deloro Mine Site

Model Segment Initial After Provincial
Guidelinea
5 yrs 10 yrs 20 yrs 30 yrs
Water (µg/L)b
Deloro to Young's Creek 5.6 2.3 - 2.4 2.3 - 2.3 2.3 - 2.3 2.3 - 2.3 25
Young's Creek to half way to Bend Bay 8.7 2.3 - 2.5 2.3 - 2.4 2.3 - 2.4 2.3 - 2.4
Remaining distance to Bend Bay 8.7 2.3 - 2.6 2.3 - 2.6 2.3 - 2.5 2.3 - 2.4
Bend Bay 8.7 2.4 - 3.6 2.3 - 3.2 2.3 - 2.9 2.3 - 2.8
Bend Bay to West Moira Lake 8.7 2.4 - 3.6 2.3 - 3.2 2.3 - 2.9 2.3 - 2.8
West Moira Lake 8.1 2.6 - 3.9 2.3 - 3.2 2.1 - 2.8 2.1 - 2.7
East Moira Lake (EML) 10.5 2.6 - 3.8 2.2 - 3.2 2.0 - 2.7 1.9 - 2.5
East Moira Lake (EML) 10.5 2.6 - 3.8 2.2 - 3.2 2.0 - 2.7 1.9 - 2.5
EML to Stoco Lake 3.2 1.0 - 1.6 1.0 - 1.4 1.0 - 1.3 0.9 - 1.2
Stoco Lake 3.2 1.5 - 1.6 1.4 - 1.5 1.3 - 1.5 1.3 - 1.4
Sediment (µ g/g)cd
Deloro to Young's Creek130 105 90 72 63 16 (LEL)
75 (SEL)
Young's Creek to half way to Bend Bay 210 159 130 93 75
Remaining distance to Bend Bay 220 166 135 96 77
Bend Bay 500 268 188 137 126
Bend Bay to West Moira Lake 200 154 126 91 73
West Moira Lake 490 266 190 140 130
East Moira Lake (EML) 225 183 153 111 89
EML to Stoco Lake 80 68 60 49 45
Stoco Lake 105 91 82 73 69

aWater quality objective from MOE (1999); sediment quality guidelines from MOE (1993).

bConcentrations in water reported as minimum to maximum levels observed in Year 5, 10, 20 or 30.

cValues in bold exceed the PWQO or the Severe Effect Level (SEL) sediment guidelines.

dSediment concentrations at the end of Year 5, 10, 20 or 30.

4.5.2 Level of Cleanup of the Deloro Mine Site Required to Meet Cleanup Objectives

Should arsenic migration from the Deloro Mine Site be essentially eliminated (e.g., 99% reduction) the model results indicate that arsenic concentrations in the Moira River at Highway 7 (which is located in the first model segment – Deloro to Young's Creek) would meet the interim PWQO during periods of high flow only (Table 4.4-16). During periods of low flow, arsenic levels would continue to exceed the interim PWQO 30 years after Deloro Mine Site cleanup. This is because a relatively small amount of arsenic from the Deloro Mine Site, coupled with relatively high background concentrations in the Moira River upstream of the mine, would still be significant relative to the interim PWQO of 5 µg/L. The interim PWQO for arsenic would be met year round in and downstream of Moira Lake within 5 years of 99% reduction in loading (Table 4.4-16). The continual release of arsenic from sediments in the bottom of Moira Lake is expected to have slight effect on arsenic concentrations in lake water, but not to the extent that the interim PWQO would be exceeded.

Table 4.4-16
Predicted Arsenic Levels Downstream Assuming a 99% Reduction in the Amount of
Arsenic Released from the Deloro Mine Site

Model Segment Initial After Provincial
Guidelinea
5 yrs 10 yrs 20 yrs 30 yrs
Water (µ g/L)bc
Deloro to Young's Creek 43.3 1.1 - 7.3 1.1 - 7.3 1.1 - 7.2 1.1 - 7.2 5.0
Young's Creek to half way to Bend Bay 52.1 1.2 - 8.5 1.2 - 8.4 1.2 - 8.4 1.2 - 8.4
Remaining distance to Bend Bay 52.1 1.2 - 8.1 1.2 - 8.0 1.2 - 7.9 1.2 - 7.9
Bend Bay 52.1 1.4 - 8.2 1.3 - 7.6 1.2 - 7.2 1.2 - 7.1
Bend Bay to West Moira Lake 52.1 1.4 - 7.8 1.3 - 7.3 1.2 - 6.8 1.2 - 6.7
West Moira Lake 53.0 2.2 - 4.7 1.6 - 3.7 1.2 - 3.1 1.2 - 3.0
East Moira Lake (EML) 76.0 2.6 - 4.0 1.9 - 3.1 1.5 - 2.4 1.3 - 2.2
EML to Stoco Lake 19.0 0.8 - 1.5 0.7 - 1.2 0.6 - 1.0 0.6 - 1.0
Stoco Lake 18.0 1.0 - 1.4 0.8 - 1.2 0.8 - 1.0 0.7 - 0.9
Sediment (µ g/g)cd
Deloro to Young's Creek 315 244 197 130 91 6.0 (LEL)
33 (SEL)
Young's Creek to half way to Bend Bay 380 294 237 156 108
Remaining distance to Bend Bay 390 300 241 157 108
Bend Bay 705 303 155 50 28
Bend Bay to West Moira Lake 370 288 234 155 108
West Moira Lake 650 231 104 33 22
East Moira Lake (EML) 375 290 231 147 99
EML to Stoco Lake 88 64 48 29 19
Stoco Lake 93 58 39 20 13

aWater quality objective from MOE (1999); sediment quality guidelines from MOE (1993).

bConcentrations in water reported as minimum to maximum levels observed in Year 5, 10, 20 or 30.

cValues in bold exceed the PWQO or the SEL.

dSediment concentrations at the end of Year 5, 10, 20 or 30.

Arsenic concentrations in surface sediments are projected to remain above the SEL for 10 years in all model segments after a 99% reduction in the amount released from the Deloro Mine Site and surrounding area (Table 4.4-16). After 30 years, arsenic would continue to exceed the SEL in all model segments, except in West Moira Lake, East Moira Lake to Stoco Lake and Stoco Lake.

The nickel PWQO of 25 µg/L is currently being met in all model segments on an annual average basis. However, exceedances occur in the section between the mine site and Bend Bay during periods of low flow (Appendix I). The PWQO would be met year-round after a 75% reduction in nickel loading (Table 4.4-17).

Nickel concentrations in surface sediments are projected to remain above the SEL in all model segments, except between East Moira Lake and Stoco Lake, 30 years after a 75% reduction in total nickel loading to Moira River (Table 4.4-17).

Model results indicate that cobalt concentrations will continue to exceed the PWQO of 0.9 µg/L as far downstream as the outlet of Moira Lake, even with the elimination of 95% of cobalt loadings from the Deloro Mine Site and adjacent area (Table 4.4-18). Below Moira Lake, cobalt concentrations would meet the PWQO within 5 years, because of the effects of dilution from the Black and Skootamatta rivers.

Following a 95% reduction in total cobalt loading from the Deloro Mine Site and surrounding area, cobalt levels in surface sediments in the Moira River between Young's Creek and Moira Lake would fall below the SLC of 296 µg/g within 20 years (Table 4.4-18). In the other model segments, sediment cobalt levels are either currently below the SLC or projected to drop below the SLC within 5 years.

Table 4.4-17
Predicted Nickel Levels Downstream Assuming a 75% Reduction in the Amount of Nickel
Released from the Deloro Mine Site

Model Segment Initial After Provincial
Guidelinea
5 yrs 10 yrs 20 yrs 30 yrs
Water (µ g/L)bc
Deloro to Young's Creek 5.6 2.5 – 14 2.5 – 14 2.5 – 14 2.5 – 14 25
Young's Creek to half way to Bend Bay 8.7 2.8-25 2.8-25 2.8-25 2.8-25
Remaining distance to Bend Bay 8.7 2.8 – 24 2.8 – 24 2.8 – 24 2.8 – 24
Bend Bay 8.7 2.9 – 22 2.8 – 21 2.8 – 21 2.8 – 21
Bend Bay to West Moira Lake 8.7 2.9 – 21 2.8 – 20 2.8 – 20 2.8 – 20
West Moira Lake 8.1 3.1 – 9.4 2.8 – 8.9 2.7 – 8.5 2.7 – 8.5
East Moira Lake (EML) 10.5 3.1 – 5.8 2.9 – 5.4 2.7 – 5.0 2.6 – 4.9
EML to Stoco Lake 3.2 1.1 – 2.1 1.1 – 2.0 1.1 – 1.9 1.0 – 1.9
Stoco Lake 3.2 1.5 – 2.1 1.5 – 2.0 1.5 – 1.9 1.5 – 1.9
Sediment (µ g/g)
Deloro to Young's Creek 130 111 100 87 80 16 (LEL)
75 (SEL)
Young's Creek to half way to Bend Bay 210 172 150 122 109
Remaining distance to Bend Bay 220 179 156 126 112
Bend Bay 500 326 266 228 220
Bend Bay to West Moira Lake 200 166 145 119 106
West Moira Lake 490 322 264 227 220
East Moira Lake (EML) 225 194 172 141 125
EML to Stoco Lake 80 71 65 57 53
Stoco Lake 105 95 88 81 79

aWater quality objective from MOE (1999); sediment quality guidelines from MOE (1993)

bConcentrations in water reported as minimum to maximum levels observed in Year 5, 10, 20 or 30.

c"Initial" nickel concentrations = nickel concentrations at the end of December; during summer low flows, nickel concentrations can increase beyond initial segment concentrations.

dSediment concentrations at the end of Year 5, 10, 20 or 30.

eValues in bold exceed the PWQO or the SEL.

Table 4.4-18
Predicted Cobalt Levels Downstream of the Deloro Mine Site Assuming a 95% Reduction in
the Amount of Cobalt Released from the Mine Site

Model Segment Initial After Provincial
Guidelinea
5 yrs 10 yrs 20 yrs 30 yrs
Water (µ g/L)bc
Deloro to Young's Creek 4.5 0.8 -3.5 0.8 -3.5 0.8 -3.5 0.8 -3.5 0.9
Young's Creek to half way to Bend Bay 10.3 0.9 -7.7 0.9 -7.7 0.9 -7.6 0.9 -7.6
Remaining distance to Bend Bay 10.3 0.9 -7.5 0.9 -7.4 0.9 -7.3 0.9 -7.3
Bend Bay 10.3 1.1 - 7.4 1.0 - 6.9 0.9 -6.5 0.9 -6.4
Bend Bay to West Moira Lake 10.3 1.1 - 7.1 1.0 - 6.6 0.9 -6.2 0.9 -6.0
West Moira Lake 9.8 1.6 - 3.8 1.2 - 3.1 0.9 -2.6 0.8 -2.5
East Moira Lake (EML) 13.3 1.8 - 2.9 1.3 - 2.3 1.0 - 1.8 0.9 -1.6
EML to Stoco Lake 3.3 0.2 - 0.8 0.2 - 0.6 0.1 - 0.5 0.1 - 0.5
Stoco Lake 3.1 0.3 - 0.7 0.2 - 0.6 0.2 - 0.4 0.2 - 0.4
Sediment (µg/g)cd
Deloro to Young's Creek 214 176 150 113 90 296 (SLC)
Young's Creek to half way to Bend Bay 490 393 329 235 179
Remaining distance to Bend Bay 505 403 337 239 181
Bend Bay 895 449 275 144 112
Bend Bay to West Moira Lake 490 399 337 243 185
West Moira Lake 490 233 140 75 60
East Moira Lake (EML) 300 249 210 149 112
EML to Stoco Lake 69 54 44 29 21
Stoco Lake 67 46 34 19 13

aWater quality objective from MOE (1999); Screening Level Concentration (SLC) calculated according to MOE (1993).

bConcentrations in water reported as minimum to maximum levels observed in Year 5, 10, 20 or 30.

cValues in bold exceed the PWQO or reference sediment concentrations

dSediment concentrations at the end of Year 5, 10, 20 or 30.

4.6 Conclusions

Results from this modelling exercise indicate that:

  • Total arsenic loading from the Deloro Mine Site and the surrounding area would have to be essentially eliminated (99% reduction) for arsenic concentrations in Moira Lake and downstream to be less than the interim PWQO of 5 µg/L during average summer low flows. Even with 99% reduction, arsenic will remain above theinterim PWQO between the Deloro Mine Site and Moira Lake at low flows.
  • Total nickel loading rates from the Deloro Mine Site and the surrounding area would have to be reduced by 75% for nickel concentrations at Highway 7 and downstream to be equivalent to, or less than, the PWQO of 25 µg/L year round.
  • Cobalt concentrations are projected to exceed the PWQO downstream of the Deloro Mine Site to East Moira Lake for the 30-year period of the model, even with 95% cleanup of the Deloro Mine Site and the surrounding area. If total cobalt loading rates were reduced by 95%, cobalt concentrations downstream of East Moira Lake are projected to drop below the PWQO following the addition of dilution water through the Black & Skootamatta rivers.
  • Arsenic and nickel concentrations in surface sediments immediately downstream of the Deloro Mine Site are projected to remain above guideline levels for some time (i.e.,> 30 years), regardless of the level of on-site cleanup.
  • Following a 95% reduction in total cobalt loading from the Deloro Mine Site and surrounding area, cobalt levels in surface sediments in the Moira River between Young's Creek and Moira Lake would fall below the SLC of 296 µg/g within 20 years. In the other model segments, downstream of Moira Lake, sediment cobalt levels are either currently below the SLC or projected to drop below the SLC within 5 years.
  • Since Young's Creek contributes relatively small amounts of arsenic, nickel and cobalt to the Moira River in comparison to discharge released directly from the Deloro Mine Site, the greatest benefit will be from cleanup efforts focussed on the Deloro Mine Site. However, there is a concern about the Deloro Mine Site derived sediments currently being held back behind a series of beaver dams on Young's Creek (see Chapters 2.2 and 5.0). Were these dams to completely fail, a significant quantity of sediment could be released to the Moira River (see Appendix VIII for a description of the results of a partial beaver dam failure in June 2000).

References

Azcue, J. M and D.G. Dixon. 1994. Effects of past mining activities on the arsenic concentration in fish from Moira Lake, Ontario. J. Great Lakes Res. 20(4):717-724.

Bosworth, W.S. and L. J. Thibodeaux. 1990. Bioturbation: a facilitator of contaminant transport in bed sediment. Environmental Progress, 9(4): 211-217.

CG&S (CH2M Gore & Storrie Ltd.). 1999. Deloro Mine rehabilitation project, development of a sitewide water and load balance - final report. Prepared for the Ontario Ministry of the Environment. May 1999.

Chapra, S.C. 1997. Surface water-quality modeling. McGraw-Hill International Editions, Civil Engineering Series, Toronto, Canada.

Cornett, R.J. and L. Chant. 1986. Speciation of arsenic and nickel in sediments of Moira Lake. Prepared for the National Uranium Tailings Program, Canadian Centre for Mineral and Energy Technology, Energy, Mines and Resources Canada, Ottawa, Canada. DSS File No. O5Gs.23241-5-1716.

Cornett, R.J., B. Risto, and L. Chant. 1987. Kinetics of arsenic and nickel in sediments in Moira Lake. Prepared for the National Uranium Tailings Program, Canadian Centre for Mineral and Energy Technology, Energy, Mines and Resources Canada, Ottawa, Canada. DSS Contract No. 23317-6-1736/OI-SQ.

Diamond, M. L. 1990. Modelling the fate and transport of arsenic and other inorganic chemicals in lakes. Ph.D. Thesis, University of Toronto, Toronto, Canada.

Diamond, M. L. 1995. Application of a mass balance model to assess in-place arsenic pollution. Environ. Sci. Technol. 29:29-42.

Environment Canada. 1994. Canadian monthly climate data and 1961-1990 normals, 1994 release. Environment Canada, Ottawa, Canada.

Environment Canada. 1999. HYDAT, Version 96 - 1.05.8: Surface water and sediment data to 1996. Atmospheric Environment Service, Environment Canada, Ottawa, Canada.

HPS (High Performance System Inc.). 1997. STELLA software and technical documentation.

MOE (Ontario Ministry of the Environment). 1972. Report on water quality in Stoco Lake. Ontario Ministry of the Environment, Toronto, Canada.

MOE. 1974. Water Resources of the Moira River drainage basin. Ontario Ministry of the Environment, Toronto, Canada. MOE Water Resources Report 6.

MOE. 1993. Guidelines for the protection and management of aquatic sediment quality in Ontario. Ontario Ministry of the Environment, Toronto, Canada. August 1993.

MOE. 1999. Water management policies, guidelines and provincial water quality objectives of the Ministry of Environment and Energy. Ontario Ministry of the Environment, Toronto, Canada. February 1999.

Mudroch, A. and J.A. Capobianco. 1980. Impact of past mining activities on aquatic sediments in Moira River Basin, Ontario. J. Great Lakes Res., 6(2):121-128.

WSC (Water Survey of Canada). 2000. Monthly water flow data from 1997 to 1999 for the Moira River.